Clermont·Development

Lake County Approves 2,241-Acre Panther Run Development Near Clermont

Lake County has approved the massive Panther Run development in South Lake County. Here's what's actually approved, what remains proposed and when construction could begin.

THE LCN BREAKDOWN
WHAT HAPPENED

The Lake County Board of County Commissioners voted 3-1 on Sept. 1 to approve the Panther Run Planned Unit Development, rezoning approximately 2,241 acres for a large mixed-use development in unincorporated South Lake County. The approval allows up to 2,624 residential units and more than 1 million square feet of non-residential development.

WHY IT MATTERS

Panther Run is not simply another subdivision. Its size, housing capacity, employment space and proposed roads and public facilities could make it a significant part of how the Wellness Way corridor between U.S. 27 and the Orange County line develops over the coming years.

WHO IT AFFECTS

The project is particularly relevant to residents of South Lake County, the Clermont area and communities near Wellness Way, where continued growth has raised questions about traffic, infrastructure, schools and preservation of open land.

WHAT CHANGES

The County Commission's approval moves Panther Run beyond its major PUD rezoning decision, but it does not mean 2,624 homes can immediately begin appearing across the property. Permitting, infrastructure work, individual phases and other development steps remain ahead.

WHAT'S NEXT

The developer currently projects groundbreaking during the first quarter of 2027, followed by clearing, grading and road work in the second quarter. Residential development is projected to begin in the third quarter of 2027, with the first residents potentially arriving about a year later.

Lake County Approves 2,241-Acre Panther Run Development Near Clermont
FULL LCN REPORT
WHAT HAPPENED

A development that could substantially reshape a large portion of southeast Lake County has received approval from county commissioners.

On Sept. 1, the Lake County Board of County Commissioners voted 3-1 to approve the Panther Run Planned Unit Development, covering approximately 2,241 acres within the county's Wellness Way planning area.

The property is located in unincorporated Lake County, rather than within Clermont city limits, and stretches generally from U.S. Highway 27 on the west toward the Orange County line on the east.

The approval allows the property to move from agricultural zoning into a Planned Unit Development designed to accommodate a mixture of residential, employment and other uses.

The approved development program allows for up to 2,624 residential units and more than 1 million square feet of non-residential development.

But the size of Panther Run — and the amount of development already occurring throughout South Lake County — has also made the project part of a broader local conversation about growth.

WHY IT MATTERS

Panther Run is significant not just because of the number of homes involved, but because of the amount of land and infrastructure being planned around them.

The project is intended to function as a master-planned community, incorporating housing alongside employment areas, roads, parks, trails and space for potential public facilities.

Developer materials currently call for more than 1 million square feet of employment uses, which the developer says could support more than 3,000 jobs. Approximately 186 acres are identified for non-residential uses.

The developer is targeting industries including medicine, finance, research and development, technology, advanced manufacturing, hospitality and tourism.

Those employment figures and industries are projections, however. They should not be interpreted as 3,000 jobs or specific employers already committed to Panther Run.

No major employer announcement is necessary for the County's approval to represent a significant change.

The approval establishes the framework under which a very large piece of the Wellness Way corridor can now progress toward development.

MORE THAN 2,600 HOMES

Housing will be one of Panther Run's most visible components.

The approved PUD allows for up to 2,624 residential units.

That's an important distinction from saying Lake County just approved construction of exactly 2,624 homes.

The number represents the development's maximum approved residential entitlement. What ultimately gets built can depend on subsequent plans, permitting, market conditions and individual development phases.

According to Panther Run's developer, residential construction is currently projected to begin during the third quarter of 2027, with residents potentially beginning to move in approximately one year later.

That would put the earliest move-ins around the third quarter of 2028, if the current schedule holds.

ROADS WILL BE A MAJOR PART OF THE STORY

For existing residents, one of the biggest questions surrounding Panther Run is likely to be transportation.

The developer says Panther Run plans include more than four miles of new roads, intended to connect neighborhoods and provide additional routes toward existing and future transportation corridors, including U.S. 27, SR 516 and SR 429.

The project's proximity to the Orange County line also makes future regional connections important to watch.

Those improvements matter because South Lake County has experienced substantial residential growth, and additional housing inevitably raises questions about how surrounding roads will accommodate additional trips.

Residents raised concerns during the approval process involving traffic, roadway capacity, growth and environmental impacts.

LCN will track the road improvements separately as Panther Run moves from approval into construction.

A POSSIBLE NEW HIGH SCHOOL

Panther Run also includes approximately 50 acres reserved for a proposed high-school site.

But there is an important distinction:

A high school at Panther Run is not yet guaranteed.

The developer says land has been set aside for a potential South Lake County high school and notes that state funding has been approved for a new high school. However, Lake County Schools ultimately determines where that school will be located.

The developer's current timeline anticipates work involving the school site beginning around the second quarter of 2028 with a 2030 target, but that should be viewed as a projected development timeline rather than a confirmed school opening date.

LCN will separately monitor Lake County School Board actions involving the proposed site.

PUBLIC SAFETY

Plans also identify approximately 8 acres for a proposed public-safety complex, potentially including a fire station and Lake County Sheriff's Office substation.

Like the school, those facilities should currently be understood as planned components of the development, not completed or operating public facilities.

The developer projects work on the fire-station and school-site components beginning in 2028, with a target around 2030.

PARKS, TRAILS AND OPEN SPACE

A substantial portion of Panther Run will not be used for buildings.

According to the developer, approximately 72.5% of the overall property is planned as lakes, wetlands, uplands and open space.

Plans also include:

20 community parks
More than 11 miles of trails
A wildlife corridor
Public open space
A trailhead with parking and amenities

The 72.5% figure deserves some context.

It should not necessarily be read as meaning nearly three-quarters of the property is newly created conservation land. The developer's calculation encompasses several categories, including lakes, wetlands, uplands and open space.

As detailed site plans progress, LCN will be able to track more precisely which areas receive permanent conservation protections and which fall into other open-space classifications.

WHAT ABOUT HOTELS AND SHORT-TERM RENTALS?

Panther Run's development plans have evolved.

Although hotel uses have been approved by Lake County, the developer currently says no hotels are planned or under contract.

Instead, some property previously associated with hotel development is now being reserved for the proposed high-school site, while other acreage is planned for tourist homes similar to short-term vacation rentals.

The developer projects those tourist homes could eventually generate approximately $6 million annually in Tourist Development Tax revenue.

That number is a developer forecast, not existing tax revenue or a guaranteed future amount.

WHO IT AFFECTS

The immediate impact is likely to be felt most strongly by residents living in and around South Clermont, Wellness Way and southeast Lake County.

But Panther Run's scale makes it relevant beyond its immediate boundaries.

Future development could affect:

Drivers, as new roads and thousands of residences alter travel patterns.

Families, as Lake County Schools considers where to place additional educational capacity in rapidly growing South Lake County.

Businesses and workers, if the planned employment centers attract significant commercial development.

Nearby property owners, as formerly agricultural land transitions into a large mixed-use community.

Residents concerned about conservation, as wetlands, open space and the project's wildlife corridor move from conceptual plans toward implementation.

WHAT CHANGES NOW?

The Sept. 1 vote represents a major milestone, but residents shouldn't expect construction across the entire property immediately.

The approval establishes the project's PUD and development entitlements.

The next stage involves turning those plans into actual infrastructure, individual neighborhoods and commercial sites.

According to the developer's current schedule:

Milestone Current projection
County PUD approval Sept. 1, 2026 — Complete
Groundbreaking Q1 2027
Clearing, grading & roads Q2 2027
Residential development begins Q3 2027
First residents Around Q3 2028
Non-residential pads available Q4 2028
School/fire-site target Around 2030

All future dates remain projected and subject to change.

WHAT'S NEXT

For LCN, the Sept. 1 approval isn't the end of the Panther Run story.

It's the point where tracking it becomes more important.

LCN has added Panther Run to the LCN Development Tracker, where we'll follow the project as it moves from county approval toward construction.

Among the next milestones we'll be watching are site-development and infrastructure permits, groundbreaking, road construction, residential plats, builder involvement, commercial and employment announcements, the proposed high-school site and public-safety facilities.

We'll also continue watching how the project addresses the traffic, infrastructure and environmental concerns raised as it moved through the approval process.

LCN BOTTOM LINE

Panther Run has been approved, but it hasn't been built.

Lake County commissioners' 3-1 vote on Sept. 1 allows the approximately 2,241-acre master-planned development to move forward with entitlements for as many as 2,624 residential units and more than 1 million square feet of non-residential development.

Groundbreaking is currently projected for early 2027, with the first residents potentially arriving around 2028.

Between those two points are permits, roads, infrastructure, individual development phases and several proposed public facilities that have yet to become reality.

LCN will track those changes as they happen.

KNOW SOMETHING WE DON'T?

Have information about this story or something happening in your community? We want to hear from you.

SEND LCN A TIP →

KEEP READING

Groveland Considers $200 Million Development, Major Land Swap
FHP reportedly investigating fatal crash near Clermont; details remain limited