·Government

Umatilla evaluates Phase 2 water-main bids ahead of anticipated November 17 award

The city’s procurement portal lists the project under evaluation. Bid-opening figures differ depending on whether an optional ground-penetrating-radar service is included.

UPDATED

Verified against the official VendorLink listing, invitation, Addendum 2 and all three scanned bid-opening pages on November 6, 2026. November 17 is anticipated only. Do not infer an award, contractor selection, accepted alternate, street locations or construction schedule. Umatilla has no existing city taxonomy row, so countywide routing is used without adding a city. Authenticated dashboard rendering remains unverified.

THE LCN BREAKDOWN
WHAT HAPPENED

The city lists ITB-26-PW-001 under evaluation after an October 29 bid opening.

WHY IT MATTERS

Base bids and the optional radar service produce different comparisons; opening figures are not contract awards.

WHO IT AFFECTS

Umatilla's water system and services connected to the mains proposed for replacement.

WHAT CHANGES

The bidding deadline has passed. No awarded contractor or construction start is established.

WHAT'S NEXT

November 17 is the anticipated award date. Verify a council decision, accepted scope and construction schedule.

Lake County News — Lake County Now. Scroll Less. Know More.
FULL LCN REPORT

LCN Report: Umatilla is evaluating bids for its Phase 2 water-main replacement project, with city procurement documents listing November 17 as the anticipated award date.

What Happened

The city's VendorLink listing identifies the project as ITB-26-PW-001, DEP Water Main Replacements, Phase 2, and marks it “Under Evaluation.” The posted bid-opening sheet is dated October 29, 2026, at 2 p.m.

The invitation calls for approximately 2,540 feet of 6-inch PVC water main and 1,450 feet of 10-inch PVC or FPVC main, using conventional installation or directional drilling. It also includes fire hydrants, connections to existing mains, reconnection of existing water services, cutting and capping old mains, and restoration work.

Why It Matters

The prices recorded at opening show why the base bid and optional work need to be considered separately. DB Civil Construction is listed at $505,390 for the base bid and $5,000 for Additive Alternate No. 1, totaling $510,390. The Kenton Group is listed at $507,084 for the base bid and $2,000 for the alternate, totaling $509,084.

Among those two entries, DB Civil's base figure is lower, while Kenton's combined figure is lower. Addendum 2 identifies the alternate as ground-penetrating-radar service to help the contractor avoid conflicts with existing utilities. The opening figures do not establish which bid the city will accept or whether the alternate will be included.

Who It Affects

The proposed work concerns Umatilla's water system and the existing services connected to the mains being replaced. The reviewed procurement notices do not establish a construction start date, a customer interruption schedule or a current street-closure schedule.

What Changes

The procurement has passed its October 29 bid deadline and is listed for evaluation. The city's published materials reviewed for this report do not establish a contract award or authorization to begin construction. A separate CDBG 23 NR Water Main Improvements solicitation, ITB-26-PW-002, is also listed under evaluation; its scope and prices are not part of the Phase 2 figures reported here.

What's Next

The invitation's projected timeline and the portal detail page identify November 17 as the anticipated award date. That is a planning date, not confirmation that an award has occurred or that the item appears on a final council agenda. The invitation reserves the city's right to reject any or all bids. An award decision, the accepted scope and a construction schedule remain to be verified.

Sources: City of Umatilla procurement listings; City invitation to bid; October 29 bid-opening sheet; Addendum 2.

KNOW SOMETHING WE DON'T?

Have information about this story or something happening in your community? We want to hear from you.

SEND LCN A TIP →

KEEP READING

Eustis News — Lake County Now. Scroll Less. Know More.
Eustis takes over Sharp’s Mobile Park purchase contract, sets Dec. 2 resident meeting
Lake County News — Lake County Now. Scroll Less. Know More.
North Lake hospital district continuation leads in unofficial returns
Groveland News — Lake County Now. Scroll Less. Know More.
Groveland parks panel to review $1.84 million project list November 10